WORK  SCHEDULE  OF CONSTRUCTION OF A RESIDENTIAL BUILDING OF…………………..

Rubble work and leveling course for foundation

Starts on 19-05-2020   to    15-06-2020

Basement work

Starts on 20-06-2020   to   02-07-2020

Earth filling inside the foundation

Starts on 02-07-2020   to   05-07-2020

RCC belt over basement

Starts on 05-07-2020   to   13-07-2020

Brick masonry up to roof level

Starts on 14-07-2020   to   03-08-2020

Roof level concrete

Starts on 05-08-2020   to   24-08-2020

Plastering works

Starts on 19-09-2020   to   21-11-2020

Wiring and Plumbing

Starts on 22-11-2020   to   28-11-2020

Truss work starts

01-12-2020  to  22-12–2020

Putty works

Starts on 01-01-2021   to   19-01-2021

Tile works

Starts on 20-01-2021  to30-03-2021

Electric, Sanitary fittings and last coat painting

Starts on03-04-2021   to   18-05-2021

 

And, then, with the blessing of God, on june, 2021 the Housewarming may be arrange.

(All the date will change according to the start date of each project)